Gouina Hydroelectric Plant

The Gouina Hydroelectric Plant (French: Centrale hydroélectrique de Gouina) is a run-of-the-river-type hydroelectric installation on Gouina Falls along the Senegal River in Mali.

It is located about 18 km (11 mi) southeast of Diamou in the Kayes Region. It is the fourth project of the Senegal River Basin Development Authority and its ground-breaking ceremony on 17 December 2013 was attended by the heads of state of each member country. Mauritanian President Mohamed Ould Abdel Aziz laid the foundation stone. Preliminary construction had been suspended due to the 2012 Malian coup d'état and subsequent Northern Mali conflict.

Gouina Hydroelectric Plant
Gouina Hydroelectric Plant
The power plant uses the natural drop of the Gouina Falls.
Official nameCentrale hydroélectrique de Gouina
CountryMali
LocationDiamou, Kayes Region
Coordinates14°00′41.40″N 11°5′59.8″W / 14.0115000°N 11.099944°W / 14.0115000; -11.099944
StatusUnder construction
Construction beganDecember 2013
Commission date2022
Construction cost283 billion FCFA
Power generation
Units under const.3 x 46.6 megawatts (62,500 hp) Kaplan-type
Nameplate capacity140 MW (190,000 hp)
Annual net output565 gigawatt-hours (2,030 TJ) (estimate)

The plant was inaugurated by the Malian Prime Minister Abdoulaye Maïga in December 2022. It cost US$329 million and the 280 km (170 mi) of transmission lines cost US$65 million. The project received 85 percent of its funding from the Exim Bank of China along with US$1 million from the EU-Africa Infrastructure Trust Fund and US$1.4 million from the International Development Association and European Investment Bank.

It has an installed capacity of 140 megawatts (190,000 hp) and will use the outflows of the Manantali Dam upstream to regulation water flow into the plant. A 1,230 m (4,040 ft) long weir just above the water fall directs water into a channel which will feed the power house just downstream of the falls. The power house contains three 46.6 MW Kaplan turbine-generators. The difference in elevation the water fall and weir provides a hydraulic head (water drop) of 22.5 m (74 ft).

See also

References

Tags:

2012 Malian coup d'étatDiamouFrench languageGouina FallsHydroelectricKayes RegionMaliMauritanian PresidentMohamed Ould Abdel AzizNorthern Mali conflictRun-of-the-riverSenegal RiverSenegal River Basin Development Authority

🔥 Trending searches on Wiki English:

MuhammadNapoleonMicrosoft Office MixTom HollandSteven SpielbergADan HurleyMarch 27ZendayaList of footballers with 500 or more goalsKaley CuocoRahul GandhiSteve BuscemiRRR (film)2023 French pension reform strikesMrBeastClient access licenseArgentinaFlipkartJonathan MajorsArnold SchwarzeneggerKabzaa (2023 film)Rupert Murdoch2023 Israeli judicial reformChristina RicciLisa BluderHimeji CastleStephen HawkingGwyneth PaltrowTina TurnerGreat Expectations (2023 TV series)The Hunger Games (film series)Tottenham Hotspur F.C.MaldivesBruce LeeNorth AmericaXVideosLewis HamiltonOrange (2010 film)Elizabeth IIMegan FoxMarlon BrandoGrace Caroline CurreyJesusGPT-4Robert Downey Jr.Hong KongWomen's Premier League (cricket)UEFA Euro 2024MalaysiaScream VIBlack Adam (film)Russo-Ukrainian WarDeaths in 2023Mike MaignanDaisy Jones & The SixJohn WayneHiroyuki SanadaThe WeekndBoston StranglerDepeche ModeParineeti ChopraChuck NorrisAfghanistanLeBron JamesTheodore RooseveltDiablo IVPathaan (film)USS Princess MatoikaCovenant School shootingRey MysterioMasterChef India (Hindi season 7)Java (programming language)Ruud van NistelrooyRegional Snowfall IndexCristiano RonaldoJim Carrey🡆 More